Week 5 Building B Construction Update
Posted: July 06, 2026 • Category: Construction and Improvements
See below for Week5 update:
- Concrete slab edge repairs continued this week.
- Slab edge repairs are substantially complete on stacks 01-03.
Outlook for Next Week (Week 6 – July 6):
- Continue slab edge repairs throughout. Predominantly focusing on stacks 04-07.
- Handrail installation should recommence on the 2nd floor next week.
- Shoring and column repair to follow once slab edge repairs are complete (likely a week or two out still)