Week 11 Update for Wild Pines
Posted: August 19, 2025 • Category: Construction and Improvements
- Waterproofing application has been completed at all elevated balconies.
- Screen enclosure installation started on Wednesday as noted last week.
- CPR personnel is currently cutting tile on the first floor. CO5 to follow for this today as I was able to get measurements for this work this morning.
- The aluminum crew has started on the 02 stack. This stack, along with the 03 stack should be close to being completed by the end of business today.
- The aluminum crew will continue to work around the building next week.
- Finish work on the small isolated walkway repairs is slated to start next week as well.