- A quarter of the 203/303 was poured back today. Concrete will need to cure until Tuesday at a minimum. Once cured, vendor will begin working on another quarter.
- Stucco repairs on lanais, with the exception of the 03 stack, will be completed today.
- Cant bead sealants are completed throughout with the exception of the 03 stack where column repairs are under way.
Outlook for Week 15
- Continue working on the 03 stack column repairs
- Being texture repairs on walkways
- Begin filling of divots on lanai floors with Sika 350 on all other stacks
- Begin hot stucco primer application on stucco repairs