Building B – Week 13 Update

Posted: August 24, 2026 • Category: Construction and Improvements

Below is an update for Week 13:

  1. Continued concrete column repairs. Most notably the 03 and 05 stacks.
  2. Unit 303 has an extensive column repair that will likely need to be tied into Unit 203. Floor protection remains in place here while vendor continues their work.
  3. Continued cant bead sealant application on surfaces with stucco. Vendor will need to add these to the columns once the shores, concrete repairs, and stucco repairs are completed.
  4. Continued stucco repairs throughout.

Outlook for Week 14:

  1. Aim to complete column repairs pending cure times and the extent of the 03 stack column repair
  2. Aim to complete stucco repairs