Building D Week 10 Update
Posted: August 11, 2025 • Category: Community
Here is Wild Pines Week 10 Update:
- Waterproofing has been completed on Stacks 01-04 as of Friday.
- Waterproofing of Stacks 05-07 is underway now. Base coat will be applied today. Broadcast coat Tuesday. Finish coat(s) on Wednesday / Thursday.
- Touch up painting and painting of slab edges that have been waterproofed starting as well. We have a guy also whipping down sliders and glass.
- Screen enclosure install is slated to start Wednesday.