Here is Wild Pines Week 10 Update:

  1. Waterproofing has been completed on Stacks 01-04 as of Friday.
  2. Waterproofing of Stacks 05-07 is underway now. Base coat will be applied today. Broadcast coat Tuesday. Finish coat(s) on Wednesday / Thursday.
  3. Touch up painting and painting of slab edges that have been waterproofed starting as well. We have a guy also whipping down sliders and glass.
  4. Screen enclosure install is slated to start Wednesday.