Wild Pines Building “D” Weekly Update – Ending July 4

Posted: July 09, 2025 • Category: Construction and Improvements

Here is the weekly update for Wild Pines:

  • Column repairs are still underway. Shoring has remained in place.
  • Waterproofing prep on elevated lanais will continue this week.
  • Application of stucco to the repaired slab edges and columns to begin this week.
  • Measurements for screen enclosure fabrication will be taken once all columns have been repaired and stucco has been applied to these repair areas.

Still moving right along.

Click here for photos of the project.