Repairs to Building D. Construction Begins Monday, June 2, 2025

Posted: May 05, 2025 • Category: Alerts

The structural repairs to the lanais on 3631 Wild Pines Building D will begin Monday, June 2 at 8am. This construction repair will include:

  1. All lanais to be locked out; doors secured; NO entry to lanais during the project
  2. All lanai screens and railings to be removed the week of June 2nd: all 21 lanais on all floors for the entire project
  3. Sliding doors to be covered with blue tinted safety plastic and plywood on lower 4 feet of all sliders
  4. All lanai floor covering to be removed down to concrete on the 2nd and 3rd floors; first floor lanais MAY have tile/flooring removed IF concrete issues discovered
  5. New metal railings /new screens to be installed on ALL lanais
  6. Waterproofing applied to concrete

 

ACTIONS NEEDED BY OWNERS IN BUILDING “D”

  1. Empty lanais of ALL furniture/furnishings/wall hangings prior to June 2
  2. Tape switches OFF for all lanais ceiling fans
  3. Inform your renters of NO ACCESS to the lanai during the construction
  4. Park cars AWAY from Building “D”

PLANNED SCHEDULE FOR CONSTRUCTION

  • Starting Tuesday May 27, delivering of materials to begin; laydown area in parking lot NEXT to the dumpster—entire area in front of the lake will be sectioned off and the parking spots in front of “D” Building will be blocked off, including the handicap spaces
  • Monday, June 2nd, full construction begins at 8am
  • 12 week planned schedule: June 2-August 30
  • Anticipated completion: September 20
  • Monday to Saturday, 8am to 5pm

 

ENGINEERING COMPANY: Velocity Engineers

PROJECT MANAGER: Gulf Breeze — Aharon Weidner 239-498-3311

CONSTRUCTION COMPANY: Custom Painting and Restoration

Owner: Steve Glazier