Building B – Week 15 Update
Posted: September 09, 2026 • Category: Construction and Improvements
Below is an update of last week’s progress (Week 15)
- Column repairs on another side of the 203/303 column is underway.
- Hot stucco primer was applied throughout the property to stucco repairs. Painting of repair areas and lanais to follow.
- The aluminium contractor was on site to measure for screen cage fabrication.
- Sikalastic 350 and sand aggregate have been applied to Stacks 01, 02, 04, and 06.
- Texture repairs are underway on walkways.
Outlook for Week 16:
- Continue isolated texture repairs on walkways.
- Continue epoxy application at the 05 and 07 stacks. 03 to follow once column repairs are done.
- Begin touch up paint.
- Possibly begin grab rail install at the courtyard stairwells.