Building B – Week 14 Update

Posted: September 01, 2026 • Category: Construction and Improvements

Below is an update for Week 14.

  1. A quarter of the 203/303 was poured back today. Concrete will need to cure until Tuesday at a minimum. Once cured, vendor will begin working on another quarter.
  2. Stucco repairs on lanais, with the exception of the 03 stack, will be completed today.
  3. Cant bead sealants are completed throughout with the exception of the 03 stack where column repairs are under way.

Outlook for Week 15

  1. Continue working on the 03 stack column repairs
  2. Being texture repairs on walkways
  3. Begin filling of divots on lanai floors with Sika 350 on all other stacks
  4. Begin hot stucco primer application on stucco repairs