Building B – Week 13 Update
Posted: August 24, 2026 • Category: Construction and Improvements
Below is an update for Week 13:
- Continued concrete column repairs. Most notably the 03 and 05 stacks.
- Unit 303 has an extensive column repair that will likely need to be tied into Unit 203. Floor protection remains in place here while vendor continues their work.
- Continued cant bead sealant application on surfaces with stucco. Vendor will need to add these to the columns once the shores, concrete repairs, and stucco repairs are completed.
- Continued stucco repairs throughout.
Outlook for Week 14:
- Aim to complete column repairs pending cure times and the extent of the 03 stack column repair
- Aim to complete stucco repairs