Building B – Week 13 Construction Update

Posted: August 17, 2026 • Category: Construction and Improvements

  1. Column repairs should be done curing today. We are aiming to strip forms on Monday, then begin working on other portions of each given column as needed.
  2. Continued stucco application on columns not receiving repairs and/or not adjacent to post shores. Slab edges are well.
  3. Patched fastener holes from the old screen enclosures. Confining prep work here.
  4. Began cant bead sealants.
  5. Handrails at stairs were test fit this week. They were shipped back to the fab shop to alter a couple angles, then will be sending them off for paint.
Outlook for next week: 
  1. Continue column repairs where needed
  2. Continue stucco repairs
  3. Continue cant beat sealants