Building B Construction – Week 7 Update
Posted: July 13, 2026 • Category: Construction and Improvements
Dear Wild Pines Owners,
See below for Week 7 Update:
- Slab repairs are mostly done. There are a few still to knock out on the 04-07 stacks once adjacent pours cure.
- Removal of stucco on columns has begun on the 01 stacks. Vendor anticipates this to continue this week as slab edge repairs finalize.
- Removal of sealant from pre-existing screen cages on columns throughout
Outlook for Week of July 13
- Aluminum crew should be back working on second floor walkway handrails.
- Continue remaining slab repairs.
- Begin column repairs if time permits.
If you have any questions, please let me know.
Thank you,
On Behalf of the Board of Directors